Portsmouth Data Center - Quarterly Excool Maintenance (NON SERVICE IMPACTING)

Completed Jul 10th, 07:00 - 18:00 BST

Timeline

Planned2 months ago

Please be advised that there will be preventative Excool maintenance at our Portsmouth data center during the following window:

From: July 10, 2017 - 07:00 BST
To: July 11, 2017 - 18:00 BST

This maintenance is required to perform preventative maintenance on the Excool units providing cooling to POD A

Data centre infrastructure and operations team will be onsite along with maintenance vendor(s) for the duration of this maintenance window.

This maintenance is scheduled as NON SERVICE IMPACTING.